Steady progress with the ground works; levelled most of the area ready for the garage footings to go in next week. Also removed the dilapidated boundary wall and cleared the trees/hedges to be replaced by a new boundary wall 19m(L) x 2m(T).
You can see the footprint of the garage starting to take shape below. Also the gap in the boundary on the left hand side where the new wall is going:
Rapidly burning through the budget with seven grab wagons required to clear the waste, hopefully just a few more to go at £200 a pop! Still a huge saving in comparison to standard builders skips, with each grab wagon taking a minimum of 3x skip loads!
The old trees/hedges were chipped and removed from site (£300). Just the problem of that giant tree stump to get rid, Will probably end up burying it, as can’t find anyone willing to take it